Jagdish Singh Rana v. M/S Delhi Buildtech Pvt. Ltd.
Case brief
What is this about?
The Delhi High Court, with parties' consent, disposed of the appeal directing the respondent to complete the project under the agreement, maintain wall thickness, and file an affidavit of undertaking. The court appointed an architect as site supervisor and ordered parties to share supervision fees.
What did the court decide?
Respondent to complete project as per agreement, maintain wall thickness, appoint court-specified supervisor, start work immediately, file undertaking affidavits.