J&K Projects Construction Corporation Ltd. v. General Manager, Northern Railways & Anr.
Case brief
What is this about?
In a petition under Section 14 of the Arbitration and Conciliation Act, 1996 seeking termination of an arbitral tribunal, the Delhi High Court returned the petition without entertaining it due to the petitioner's failure to establish territorial jurisdiction, as part of the cause of action arose outside Delhi.
What did the court decide?
The petition was returned as it was not entertained due to lack of established territorial jurisdiction.