Alstom T & D India Ltd. v. M/S Rakesh Brothers
Case brief
What is this about?
The court disposed of two OMPs challenging an arbitration award. Upholding the arbitrator's award of Rs. 65 lakhs for rectification costs by third parties upon proof of purchase orders, it rejected the claim for the full liquidated damages amount and dismissed objections regarding interest.
What did the court decide?
Both OMPs were dismissed; the arbitration award upholding Rs. 65 lakhs expenses against Rs. 84 lakhs retention was affirmed.