Rekha Mishra v. M/S Bses Rajdhani Power Ltd.
Case brief
What is this about?
This order in a writ petition wherein the petitioner sought direction to grant a new electricity connection held that upon completion of formalities, the respondent must grant the connection within 48 hours thereafter, and accordingly disposed of the petition.
What did the court decide?
Petitioner to complete formalities; respondent to grant electricity connection within 48 hours thereafter.