The court extended the arbitration proceedings timeline until 17th August, 2018 by six months upon joint request of both parties due to expiration of the original period.
The court extended the arbitration proceedings timeline until 17th August, 2018 by six months upon joint request of both parties due to expiration of the original period.
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
$~31
..... Decree Holder Through : Mr.Dhruv Madan, Adv.
versus
MUKESH AGGARWAL
..... Judgement Debtor
Through : None
CORAM: HON'BLE MR. JUSTICE YOGESH KHANNA O R D E R
% 05.02.2018
It is submitted by learned counsel for the petitioner that the period of conducting proceedings before the arbitrator is going to expire on 16th February, 2018. By joint petition the parties request the period for arbitration proceedings be extended for six months. In view of the request the time period for conducting the arbitration proceedings is extended till 17th August, 2018.
The petition is disposed of.
Order dasti under the signature of the Court Master.
YOGESH KHANNA, J
FEBRUARY 05, 2018 VLD