The Deputy Secretary v. M/S Bhayana Builders Pvt. Ltd.
Case brief
What is this about?
The Delhi High Court dismissed an appeal against a Part Award in an arbitration dispute. The court held that the arbitrator correctly allowed claims for withheld liquidated damages due to employer-caused delay and granted price escalation for the extension period based on law and orders, finding no perversity in the award.
What did the court decide?
The appeal filed under Section 37(1)(C) of the Arbitration and Conciliation Act, 1996 was dismissed. The interim stay application was also dismissed.