Power Grid Corpn.of India Ltd. v. Karnataka Power Transmission Co.
Case brief
What is this about?
The High Court dismissed the appeal challenging the CERC's rejection of a review petition regarding Interest During Construction (IDC). The court held that the Commission correctly applied CPC provisions for review, rejecting new evidence that contradictedly admitted delay, as it amounted to a new proceeding rather than a review of existing record.
What did the court decide?
The appeal and the review application were dismissed, upholding the CERC's order reducing the IDC claim.