S & P Infrastructure Developers (P) Ltd. & Anr. v. National Highways and Infrastructures Developers Corporation Ltd. & Anr.
Case brief
What is this about?
This court ordered the release of Rs. 2.32 crores deposited by the petitioner to the respondent to secure a bank guarantee. The petitioner was directed to file a representation to retain the project without the aggrieved joint venture partner. The court clarified that the respondent would decide independently on the project continuation and that the bank guarantee would be returned upon receiving
What did the court decide?
Deposit of Rs. 2.32 crores released to respondent; liberty to seek continuation of project without the barred JV partner; original bank guarantee to be returned after refund.