Alcon Builders & Engineers (P) Ltd. v. Northern Railways
Case brief
What is this about?
In this interim habeas-like petition under Clause 40.1 of a construction contract, the petitioner sought appointment of an arbitrator after the respondent failed to act on a demand for outstanding dues and ignored prior requests for arbitration. The respondent did not appear.
What did the court decide?
Appointed Justice (Dr.) Bharat Bhushan Parsoon as arbitrator; fee to be fixed by Delhi High Court Arbitration Centre.