M/S Priyanka Overseas Pvt.Ltd v. Joongang Shipping Co. Ltd.
Case brief
What is this about?
This Section 34 petition challenged an arbitral award on charter party agreement disputes. The Court observed inconsistencies in the award regarding deviation charge calculations. It held that for deviation charges, the petitioner should be paid based on the shorter, justified voyage period plus bunkering/checkpoint days. The restriction on delayed payment counter-claims was vacated due to lack of
What did the court decide?
Deviation charges remanded to be calculated at USD 6,000 per day for 9.6388 days; counter-claim for USD 48,082.19 allowed; other objections rejected.