Somdatt Builders-Ncc-Nec (Jv) v. National Highways Authority of Indi
Case brief
What is this about?
The petitioner challenged arbitration proceedings management regarding a pending Section 34 petition. The Court held the petition was premature because a challenge under Section 34 of the Arbitration and Conciliation Act was already pending adjudication. The petitioner must file a fresh petition after the outcome of the pending Section 34 petition.
What did the court decide?
Petition dismissed as premature. Liberty to file a fresh petition based on the outcome of the pending Section 34 petition.