(hereafter 'the Agreement') after it successfully bid in a tender process floated by the Respondent, through the Ministry of Health and Family Welfare (hereafter “the Principal”). The agreement involved the supply, installation, testing and commissioning of electrical equipment(s). The total contract value was ` 41,20,09,326/-. The completion period of the contract was 16 months, starting from 19.08.2011. Ahluwalia alleged that the Principal did not hand over the entire site till December 2015. In the meanwhile, the tenure of completion under the Agreement was extended eleven times. Accordingly, it alleged that delays in the performance of the Agreement – attributable - to the Principal’s acts and omissions, resulted in losses to it. It claimed compensation. The Principal refuted these allegations and blamed Ahluwalia for the delays; it further alleged that in terms of the General Conditions of Contract (hereafter 'GCC'), no compensation was payable for any delay in handing over of the site. Since these disputes could not be resolved through mutual negotiation, they were referred to arbitration, in terms of a condition under the contract.