“A close analysis of the above provisions would reveal that Section 19 enables the acquisition process by the appropriate Government issuing a declaration, Section 19 (6) is an important exception in that it imposes a limitation on the power itself (i.e limitation for making declaration). In case the time limit is not adhered to, the acquisition lapses. The proviso to Section 19 (6) recognizes that sometime Court intervention by interim orders impede the appropriate Government from issuing declarations. Section 69 (2) enables increased compensation; yet, the explanation provides that if the landowner secures an interim order, the period spent in litigation, particularly when the interim order subsists, cannot be given benefit to him while calculating interest. Thus, limitation of power freshly conferred or created by the Act does not follow a uniform pattern. The object of the provision in question defines how the allusion to interim orders of court are dealt with. However, Section 24 (2) is a special provision that but for its enactment, would have resulted in the operation of the General Clauses Act, 1897 in that all action taken under the old law would have been preserved. It therefore had to be construed in the context of the old enactment which clearly contemplated exclusion of time at the different stages when interim orders subsisted (i.e to make declaration after preliminary notification and also extended period for making the award). These perspectives are indicative of a contrary interpretation. However, this Court notices that the ruling of the Supreme Court on this aspect is decisive; it consequently binds it.”