M/S Tarouni Construction & Finance (P) Ltd. v. Union of India and Ors.
Case brief
What is this about?
The Court declared suit lands free from acquisition under Section 24 (2) of the Rights to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, as neither possession nor compensation was completed within the statutory timeframe.
What did the court decide?
Declaration issued that the suit lands are free from acquisition and the acquisition is deemed to have lapsed.