Municipal Corporation of Delhi v. Ravi Kumar
Case brief
What is this about?
The High Court of Delhi dismissed petitions challenging an arbitration award where a respondent claimed payment for additional work and demolition. The Court held that statutory provisions allowed compensation for work done without a formal contract, and the quantification of demolition costs, while based on supposition due to lack of evidence, was not unreasonable. Consequently, the arbitrator's
What did the court decide?
Petitions dismissed with no order as to costs; arbitrator's award on additional work, demolition costs, interest, and costs stands upheld.