Shreeniwas Cotton Private Limited v. Union of India & Anr.
Case brief
What is this about?
This High Court held that the respondents were unjustified in ignoring requests for ICAO aeronautical studies required for building height clearance near Mumbai Airport. The court directed the authorities to refer specific petitions for such studies within two weeks, with costs borne by the petitioners, and to decide on height permissions within four weeks of receiving the report.
What did the court decide?
The respondents were directed to refer the petitioners' matters to ICAO for an aeronautical study within two weeks, with petitioners bearing costs, and to decide on height permissions within four week