Hindustan Steelworks Construction Ltd. v. NTPC Ltd. Kahalgoan Super Thermal Power Station & Ors.
Case brief
What is this about?
This order dismisses a petition under Section 34 of the Arbitration and Conciliation Act, 1996 seeking to set aside an award from the Permanent Machinery of Arbitration (PMA). Relying on Supreme Court precedent, the court held PMA awards are outside the Act's scope. Pending further instructions from the respondent company regarding arbitration under the Act, the court formulated a four-week timeli
What did the court decide?
Petition dismissed. Respondent's Chairman/Cum Managing Director to decide on arbitration referral within four weeks. Parties to endeavour mutual appointment of Sole Arbitrator if agreed.