the aforesaid plot, consists of basement, ground, first, second and third floors. The building plan of the ground floor was sanctioned in the year 2001. Thereafter in the year 2005 a fresh application was made by the petitioner for grant of sanction in respect of the basement and ground floor. The completion certificate in respect of these two was granted in the year 2006. On 1.3.2007, the petitioners made a fresh application for raising first, second and third floors in terms of the DDA notification dated 22.7.2006. The sanction was accorded subject to payment of Rs.2,37,854/- as processing charges. On 7.5.2007, the Supreme Court in a batch of writ petitions had banned construction of third floor on the plotted houses in Delhi. Thus, the permission which was given to the petitioner was confined only to the first and second floor subject to payment of a sum of Rs.91,349/-. This sanction was granted on 3.9.2007. Pursuant to the sanction granted, the petitioner raised the construction on the plot of land in question. The petitioner applied for permission in terms of the provisions of MDP 2021 to run a bank on the ground floor and the basement from the DDA which was granted to the petitioner on 15.2.2008 subject to his depositing a sum of Rs.2,22,676/- with the MCD. This was despite the fact that the services of the colony were not transferred to the MCD and the aforesaid charges stood deposited on 1.1.2009 and thus the permission to run the bank from the ground floor and the basement was granted. On 1.9.2008 only a fresh application for construction of third floor was made as the ban imposed by the Supreme Court was lifted. The DDA inspected the site on 20.9.2008 and after charging the processing fee of Rs.2,07,000/-, the permission to raise the third floor construction was granted which was completed on 15.12.2008.