Peelaram Pal v. Bank of Baroda
Case brief
What is this about?
Chhattisgarh High Court (Bilaspur), WPS No. 4506 of 2026, Bibhu Datta Guru, J., 17/06/2026: dismissal of writ petition challenging discontinuation of petitioner's engagement as Business Correspondent (BC) Supervisor of Bank of Baroda by communication dated 06.04.2026 (Annexure P/4) and relieving order dated 05.05.2026 (Annexure P/8). Contractual termination clause allowing either party to end the contract on 30 days' notice was held satisfied; no arbitrariness or natural-justice violation; petitioner cannot claim rights dehors the contract; petition dismissed.
What did the court decide?
On perusal of the contractual stipulation and the impugned communication dated 06.04.2026 (Annexure P/4), either party was entitled to terminate the contract by giving 30 days' notice, and the record shows the respondent-Bank had issued communication dated 06.04.2026 granting 30 days' notice prior to the relieving order dated 05.05.2026 (Annexure P/8).