Progressive Mining Product v. State of Chhattisgarh
Case brief
What is this about?
This writ petition challenged the non-payment of a bill of Rs. 4,80,000 for supply of Alumino-Ferric to the Municipal Council, Manendragarh. The High Court, observing that there was no dispute regarding the supply of materials, directed the concerned authority to consider the petitioner's representations and decide them. The court ordered the payment of the outstanding amount within 60 days if no dispute existed on the supply of materials, without expressing an opinion on the merits of the claim.
What did the court decide?
Directed the concerned authority to consider the petitioner's representations and decide the same. If there is no dispute regarding the supply of materials, directed payment of the due amount to be made within 60 days.