M/S. Menakshi Con v. South Eastern Coalfields Limited (S E C L)
Case brief
What is this about?
SECL Kusmunda GeM tender; cancellation of Letter of Acceptance; forfeiture of performance security deposit; bank guarantee encashment; Clause 6.1 General Terms and Conditions; Clause 13.3 dispute resolution mechanism; force majeure office memorandum 29.04.2026; West Asia conflict; diesel price escalation; Price Variation Clause; banning/debarment proceedings; SPLT disqualification; judicial review restraint in tender and contractual matters; Article 226 writ dismissed; State of U.P. v. Bridge & Roof; Joshi Technologies; Banshidhar Construction; Tata Motors BEST; Michigan Rubber; Jagdish Mandal; Meerut Development Authority; Municipal Corporation Katra; High Court of Chhattisgarh at Bilaspur; WPC No. 3673 of 2026; Ramesh Sinha Chief Justice; Ravindra Kumar Agrawal Judge.
What did the court decide?
No relief granted; writ petition dismissed. Dismissal shall not preclude the petitioner from availing any remedy available under the dispute-resolution mechanism contained in the agreement or in accordance with law; no order as to costs.