Smt Sarla Devi Agarwal v. Executive Engineer
Case brief
What is this about?
Chhattisgarh High Court, Bilaspur; ARBA No. 45 of 2025 & ARBA No. 44 of 2025; Justice Naresh Kumar Chandravanshi; arbitration appeal under Section 37 Arbitration & Conciliation Act 1996; National Highway land acquisition compensation; Arbitrator / Additional Commissioner Bilaspur Division; Case Nos. 4 v-82/2017-18 and 5 v-82/2017-18; Misc. Civil Suit No. 26/19 and 22/19, Third District Judge Janjgir; order set aside for violation of natural justice; no notice or hearing to Executive Engineer National Highway; remand to Arbitrator for fresh hearing and disposal; 90-day compliance timeline; appellants Ritesh Kumar Agarwal and Smt. Sarla Devi Agarwal; counsel J.A. Lohani, Ramakant Mishra (DSGA), Ujjawal Choubey.
What did the court decide?
Both arbitration appeals allowed; the orders dated 06.02.2025 (Misc. Civil Suit No. 26/19) and 30.09.2024 (Misc. Civil Suit No. 22/2019) of the Third District Judge, Janjgir, and the arbitral orders dated 15.11.2017 in Case Nos. 4 v-82/2017-18 and 5 v-82/2017-18 set aside; matters remitted to the Arbitrator / Additional Commissioner, Bilaspur Division to restore both cases and dispose of them afresh in accordance with law after affording due opportunity of hearing to the parties, within 90 days.