Ram Baran Chaurasia v. State of Chhattisgarh
Case brief
What is this about?
Chhattisgarh High Court, Bilaspur; WPS No. 2618 of 2023; Ram Baran Chaurasia v. State of Chhattisgarh and others; suspension of Sub Engineer/Sub-Divisional Officer, Water Resources Division Kondagaon; dismissal of departmental appeal by State Government (01.03.2023); recommendations for revocation of suspension by Engineer-in-Chief and Chief Engineer, Mahanadi Project (22.04.2024, 13.06.2024); writ direction/mandamus to State to take decision on recommendations within 60 days; limited prayer; petition disposed of; single bench of Ravindra Kumar Agrawal, J.; order dated 24/06/2025; NAFR.
What did the court decide?
Limited relief only: direction to respondent No. 1 (State) to decide on the recommendations of respondents No. 2 and 3 (Annexures P/9 and P/10) within 60 days in accordance with law on its own merits, with petitioner to furnish a copy of the order within a week; the substantive challenge to the suspension and the appellate dismissal was not adjudicated.