Suyash Dubey v. State of Chhattisgarh
Case brief
What is this about?
Writ petition (Article 226) by L-1 bidder challenging cancellation of e-tender dated 28.10.2024 (system Nos. 160699, 160700) and fresh e-tender dated 26.12.2024 (system Nos. 163469, 163475) by Nagar Panchayat Malhar, Bilaspur; cancellation caused by inadvertent opening of ineligible bidders' tenders (Sub-Engineer report; Annexure R-3/5); held cancellation of entire tender process justified, no favoritism; judicial restraint in tender matters per N.G. Projects Ltd. v. Vinod Kumar Jain (2022) 6 SCC 127 and Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Ltd.; petition dismissed, no costs, liberty to participate in fresh NIT.
What did the court decide?
None; petition dismissed with no order as to costs, the petitioner being at liberty to participate in the fresh NIT floated by respondent No. 3 if he fulfils its terms and conditions.