M/s Triveni Turbine Limited v. M/s Bhagwati Power And Steel Limited
Case brief
What is this about?
Letter of intent (LOI) as concluded/binding contract — terms of LOI decisive (South Eastern Coalfields v. S. Kumar's Associates AKM (JV), (2021) 9 SCC 166; Dresser Rand S.A. v. Bindal Agro Chem Ltd and Khosla Compressors Ltd., (2006) 1 SCC 751); forfeiture of advance/earnest money requires clear and explicit clause (Satish Batra v. Sudhir Rawl, (2013) 1 SCC 345); interest as damages under Section 73 Contract Act requires proof/assessment of loss (Welspun Specialty Solutions v. ONGC, (2022) 2 SCC 382); Section 74 Contract Act forfeiture plea; refund of Rs.30 lakh advance; 9% interest set aside, 6% default interest after 45 days; opportunity to lead evidence under Order 17 Rule 1 r/w Section 151 CPC. Parties: M/s Triveni Turbine Limited (appellant/defendant) v. M/s Bhagwati Power And Steel Limited (respondent/plaintiff); High Court of Chhattisgarh at Bilaspur, FA No. 328 of 2017, pronounced 14-02-2025 (reserved 6-1-2025); coram Rajani Dubey & Narendra Kumar Vyas, JJ (author: Vyas J).