Shriram General Insurance Co. Ltd., v. Kekti Dhruv
Case brief
What is this about?
condonation of delay; civil revision; MACT No.1029/2024; 3rd Additional Motor Accident Claims Tribunal Raipur; Order 7 Rule 11 CPC; Section 166(3) Motor Vehicles Act 1988; six months limitation; Section 5 Limitation Act; Section 159 Motor Vehicles Act; Section 166(4) Motor Vehicles Act; First Accident Report FAR; Detailed Accident Report DAR; Annexure XIII Central Motor Vehicles Rules; Cholamandalam MS General Insurance v Shreelakshmi T SLP(C) 9152/2023; Akshay Raj 2023 LiveLaw (Ker) 50; SLP (Civil) Diary No.23834/2023; Malrawan v Praveen Travels 2023 SCC Online Madras 5467; Shriram General Insurance; Kekti Dhruv; Parmeshwar Dhruv; no final award till Supreme Court decision; Deepak Kumar Tiwari
What did the court decide?
Delay of 23 days in filing the Civil Revision condoned (I.A. No.01/2025 allowed); Claims Tribunal directed not to pass final award in Claim Petitions pending before it till the Supreme Court conclusively decides the Section 166(3)/DAR issues, and to reconsider the application and pass a fresh order thereafter.