Govind Kumar Mishra v. Shyam Sundar Agrawal
Case brief
What is this about?
Specific performance; Section 16(c) Specific Relief Act 1963; readiness and willingness; time essence of contract; six-month stipulation in agreement dated 14.07.2003; Survey No. 218/2 Village Jagatpur Raigarh; notice Ex. P/7 unserved; postal receipt Ex. P/19 wrong name; earnest Rs.20,000/- refunded by banker's cheque Ex. D/1 on 23.03.2006; financial capacity Rs.1,80,000/- Punjab National Bank PW-3; K.S. Vidyanadam (1997) 3 SCC 1; Pydi Ramana AIR 2024 SC 3242; J.P. Builders (2011) 1 SCC 429; Chand Rani (1993) 1 SCC 519; First Appeal No. 125 of 2010; High Court of Chhattisgarh Bilaspur; neutral citation 2024:CGHC:35686; decided 11.09.2024 by Rakesh Mohan Pandey, J.; appeal dismissed, no costs.
What did the court decide?
Standard applied: Section 16(c) of the Specific Relief Act, 1963 makes continuous 'readiness and willingness' a condition precedent with the onus on the plaintiff; adopting the Supreme Court's exposition (Pydi Ramana; J.P. Builders), 'readiness' is the plaintiff's capacity to perform, including financial position to pay the consideration, and 'willingness' is the conduct of the party.