Sh. Sunder v. MCD
Case brief
What is this about?
The Tribunal allowed the claimant's application for arrears under Section 33-C(2) of the Industrial Disputes Act, 1947. Relying on the management's categorical admission of Rs. 41,784, the court directed payment within 30 days and imposed a 6% interest liability for delayed payment.
What did the court decide?
Directed the management to pay Rs. 41,784 within 30 days; imposed 6% interest from the date of order till realization.