have been prescribed. So far as the Wind RPO is concerned, the same can only be met by energy produced from WPPs commissioned after 31st March 2022. Therefore, in this context the energy produced from WPPs commissioned after 31st March 2022 cannot be substituted by energy produced from other WPPs ( i.e. , WPPs commissioned before 31st March 2022). Similar is the case for HPO and Other RPO. Therefore, it would be relevant to assess the horizonal overlaps considering the segmentation made by the RPOs. In the instant matter, within the renewable power generation segment, the activities of the Acquirer group and the target entities exhibit or would exhibit (considering under construction and under development projects) horizontal overlaps with regard to generation of power from wind projects commissioned after 31st March 2022, and other renewable power sources. The combined market shares of the Acquirer group and the target entities for overlapping segments and sub-segment are [0-5]%.