Kalomoni Basak and Ors. v. State of West Bengal and Ors.
Case brief
What is this about?
Sand mining lease extension refused; force majeure clause; Covid-19 pandemic; water logging/flood from untimely release of water by Tilpara Barrage (December 2021 to March 2022); Mayurakshi river bed, Mouza Kenduli, P.S. Suri, Dist. Birbhum; plot no. 01/2050(B); environmental clearance dated 04.06.2018 ceiling of 35,820 cubic metre per annum; Sustainable Sand Mining Management Guidelines 2016; Rule 51 West Bengal Minor Minerals Concession Rules 2016 appellate order; judicial review under Article 226/227 of administrative decision on State contract; Subodh Kumar Singh Rathour (2024) 15 SCC 461; legal injury; concurrent findings not re-appreciable in writ jurisdiction; CREDAI vs. Vanashakti (2026) 5 SCC 201; writ petitions dismissed.
What did the court decide?
The contention of the writ petitioners that they could extract more sand than the ceiling in the environmental clearance report dated 04.06.2018 and/or the registered deed of lease dated 14.06.2018 has no leg to stand upon: the Environmental Authority restricted extraction to 35,820 cubic metre per annum, that finding was never challenged by the original lessee or the writ petitioners, and the lease was executed only on submission of the said clearance.