Debasish Panda v. State of West Bengal and Ors.
Case brief
What is this about?
Petitioner alleged his property was used for laying railway tracks under the Deshapran-Nandigram project without payment of compensation and his representation dated 25 September 2024 remained undecided. Court directed the Divisional Railway Manager to forward the representation to the Deputy Chief Engineer (Con)/Land, South Eastern Railway, who must decide after hearing and pass a reasoned order
What did the court decide?
DRM, SER directed to forward representation dated 25.09.2024 to Deputy Chief Engineer (Con)/Land to decide after hearing within 8 weeks; consequential steps if decided in petitioner's favour.