Rup Narayan Agarwal v. Nobel Developments Private Limited and Ors.
Case brief
What is this about?
Intra-court appeal against an order permitting shifting of the appellant's commercial electricity meter to the promoter's new building's meter room. CESC confirmed no hazard existed and there was no bar to the meter staying put; consent recorded by the Single Bench was conceded incorrect. Appeal allowed and impugned judgment set aside.
What did the court decide?
Impugned judgment dated 7 January 2026 set aside; appeal allowed; CAN 1 of 2026 disposed of.