Disputes arose under a road repair contract providing for arbitration by a sole arbitrator under Condition 70 of the GCC. The court found the claims live, the arbitration agreement invoked, and the contractual appointment mechanism eliminated by amendment and Supreme Court rulings. By consent, it appointed a sole arbitrator.
What did the court decide?
Ms. Anjili Nag, Senior Advocate, appointed Sole Arbitrator to adjudicate the contractual disputes; fees and costs shared equally by the parties.