Ms v. Bro Engineering Services v Union of India
Case brief
What is this about?
Execution of arbitral award; delay by Trial Court in issuing notice to award-debtors; six-month timeline for disposal of execution proceedings with written-reasons extension; Periyammal (2025) 9 SCC 568 para 42.12; Rahul S. Shah (2021) 6 SCC 418 para 42; Commercial Court at Asansol; Misc. Execution Case (Commercial) No. 02 of 2025; AO(COM) 5 of 2026; V-Bro Engineering Services Vs. Union of India; directions to serve notice within a week; affidavit of assets; no costs; disposed of.
What did the court decide?
Directions issued: appellant to serve notice of the execution application on the award-debtors within a week; award-debtors to secure the quantum of award and/or file affidavit of assets as per the Trial Judge's decision; Trial Judge to dispose of the Misc. Execution application expeditiously in terms of the Supreme Court's directions. No order as to costs.