Dhirendra Nath Singh and Ors. v. West Bengal State Electricity Distribution Company Limited and Ors.
Case brief
What is this about?
WPA 9378 of 2024 (Biswanath Mondal & Anr.) and WPA 25272 of 2024 (Dhirendra Nath Singh & Ors.) vs West Bengal State Electricity Distribution Company Limited & Ors.; way leave dispute; electricity connection through disputed private passage; order dated 21.11.2023 of District Magistrate, South 24 Parganas under Rule 3(1)(b) Works and Licensee Rules 2006; Rule 3(2) compensation for landowner; rayati land vs common passage; alternative route contention; reliance on AIR 2012 Cal 205 Sk. Samsud Doha vs WBSEDCL; no interference with factual finding under Article 226; police assistance for effecting connection at cost of connection-seekers; connection within four weeks; compensation order within three months; disposed 05.08.2025.
What did the court decide?
Both writ petitions disposed of by common order: the challenge to the District Magistrate's order fails (no interference); WBSEDCL directed to effect the electricity connection to the WPA 25272 of 2024 petitioners through the passage within four weeks, with local police assistance whose cost is borne by those petitioners; District Magistrate directed to pass a compensation order under Rule 3(2) within three months.