Buddhadeb Singha and Ors. v. the State of West Bengal and Ors.
Case brief
What is this about?
Land requisitioned in 1990 under the West Bengal Land (Requisition and Acquisition) Act, 1948 was never acquired, as no Section 4(1a) notification issued before the Act lapsed in 1997. The court held the acquisition incomplete and directed initiation of proceedings under the 2013 Act to determine and disburse full compensation within 180 working days.
What did the court decide?
Direction to respondent no.5 to initiate acquisition under Act XXX of 2013 and disburse compensation within 180 working days.