New Parijat Cooperative Housing Society Limited & Anr. v. Kolkata Metropolitan Deve. Authority & Ors.
Case brief
What is this about?
KMDA penal charges delayed construction; Kolkata Metropolitan Development Authority; cooperative housing society Baishanabghata-Patuli Patuli Project; plot F/145; lease deed dated 21.08.2000 clause 2(b)(iii) clause 4(i); non-statutory contract; no public law element; Article 226 maintainability; Article 14 arbitrariness; Pricing Committee administrative policy; judicial review of policy decision; Punjab State Power Corporation v Emta Coal applied; Radhakrishna Agarwal applied; Orissa Agro Industries applied; LIC v Escorts; Bareilly Development Authority; Siddhartha Co-operative Housing Society distinguished; Damodar Prasad Agarwal referred; demand Rs. 42,94,981/- penal charges service tax; writ dismissed WPA 1432 of 2016.
What did the court decide?
The penal demand is not supplemented dehors the contract: the lease (Clauses 2(I)(b) and 2(II)) already contemplated rents, taxes, charges and impositions payable from time to time, so the imposition of penalty is a species emanating from the terms of the contract rather than an alteration of it.