West Bengal Industries Infrasture Development Corporation v. Dropadi Devi Bhagalewala and Ors.
Case brief
What is this about?
Lapse of acquisition notice under Section 7A of the Act of 1948 (West Bengal Land (Requisition and Acquisition) Act); Section 4(1a) notice dated 02.02.1990; award published 19.09.1995 beyond the 31.03.1995 outer limit under the proviso to Section 7A; Explanation regarding court-stay exclusion; revival of original owner's title; subsequent purchaser locus standi; Act of 1948 not pari materia with the Act of 1894; migratory provisions not availed; Indore Development Authority (2020) 8 SCC 129 distinguished; Sabita Mondal (2011) 3 CHN 555 followed; Mihir Kumar Sarkar AIR 1972 Cal 8 relied on; Laxmi Devi (2015) 10 SCC 241; Lila Deb Chowdhury (2002) 1 Cal LT 278; Shiv Kumar & Anr.; Savita (2019) 10 SCC 29; unexplained delay of 30 years in writ petition; Malda, Mouza Jadupur, Plot Nos. 1117/1203, 1118, 1119; WPA 18345 of 2017; MAT 178 of 2024 with CAN 2 of 2024.
What did the court decide?
No relief to the appellant; the appeal was found to have no merit and MAT 178 of 2024 along with all connected applications (including CAN 2 of 2024) were disposed of without any order as to costs.