Kinkar Chandra Biswas v. the West Bengal State Electricity Distribution Company Limited and Ors.
Case brief
What is this about?
Electricity connection writ, Calcutta High Court, W.P.A. 26728 of 2023, Kinkar Chandra Biswas v. WBSEDCL & Ors., Sabyasachi Bhattacharyya J.; directions for fresh inspection on prior notice, quotation/offer letter, and supply of electricity connection subject to compliance (submersible pump, meter room); timelines of one week / one week / fortnight; no costs; no statute or precedent cited.
What did the court decide?
Writ petition disposed of with directions to WBSEDCL: (i) further inspection on prior notice within a week; (ii) if formalities complied with, raise quotation/offer letter within a week thereafter; (iii) give electricity connection within a fortnight of the petitioner's compliance, if feasible otherwise; no order as to costs. ¶13