What is this about?
In a PIL under Article 226, CESC was permitted to enhance the electricity load for its connection owned by the petitioner, second wife, enabling her to use it for the first floor flat despite existing litigation regarding the flat's possession.
What did the court decide?
Petitioner permitted to apply for enhancement of load on existing meter for second floor; CESC to raise quotation and enhance load within a week; petitioner can use enhanced load for first floor.