Asit Patra v. State of West Bengal and Ors.
Case brief
What is this about?
Writ petition seeking electricity connection. Court directed WBSEDCL to provide connection over a viable route identified by the Company, directing installation of poles within four weeks. Police assistance directed if obstruction occurs. Costs issue noted. Petitioner empowered by Section 43, Electricity Act, 2003.
What did the court decide?
Directing WBSEDCL to provide electricity connection over the suggested route within four weeks. Police assistance directed if obstruction is raised by others.