Biswajit Ghosh v. Cesc Ltd. and Ors.
Case brief
What is this about?
In this writ petition, the petitioner filed a complaint seeking an electricity connection which was refused by the respondent on grounds of apprehended load splitting. The matter remains pending before the Grievance Redressal Officer. The Court disposed of the petition directing the Officer to decide the dispute expeditiously.
What did the court decide?
Directing the Grievance Redressal Officer, CESC Limited, to decide the petitioner's dispute regarding the electricity connection application expeditiously within four weeks.