Dnyanoba Patloba Kendre v. the State of Maharashtra and Others
Case brief
What is this about?
Aurangabad Bench, Bombay High Court; W.P. No. 1751/2026; neutral citation 2026:BHC-AUG:15347-DB; decided 10-04-2026; Section 28-A Land Acquisition Act 1894; re-determination of amount of compensation; direction/mandamus to respondent No. 2 (State authority); six-month timeline; AGP statement taken as undertaking; writ petition disposed; petitioner Dnyanoba Patloba Kendre; advocates G. K. Sontakke (petitioner) and A. M. Phule, AGP (respondent Nos. 1 and 2); bench Vibha Kankanwadi and Hiten S. Venegavkar, JJ.
What did the court decide?
Direction to respondent No. 2 to decide the application under Section 28-A of the Land Acquisition Act, 1894 for re-determination of amount of compensation within a period of six months from the date of the order; the AGP's statement recorded as an undertaking. ¶11