Manda Vinod Jadhav and Others v. the State of Maharashtra and Others
Case brief
What is this about?
Revenue Recovery Certificate execution; delay in executing recovery certificate since 03.06.2024; Employees' Compensation award of Rs. 6,39,200/- with 12% interest from 18.08.2017; Workmen's Compensation Application No. 19/2018; Collector Sambhajinagar; certificate wrongly forwarded to Gangapur, recovery at MIDC Waluj Aurangabad; direction to respondent No. 2 to execute within three months; writ petition disposed; Bombay High Court Aurangabad Bench; legal heirs of workman dead in chemical drum blast (death 25.08.2017); joint and several liability of employer respondents 3 and 4.
What did the court decide?
Direction to respondent No. 2 to execute the Revenue Recovery Certificate and recover the compensation from respondent Nos. 3 and 4 within three months from the date of the order; writ petition disposed of accordingly. ¶14