Asset Reconstruction Company India Ltd. v. Dr K Senthilnathan
Case brief
What is this about?
Extension of time; condonation of delay in filing appeal; last chance extension; Section 372 Cr.P.C. leave to appeal before Sessions Court; withdrawal of criminal application with leave to appeal; eight weeks time extended by four weeks; order dated 12 November 2025; asset reconstruction company as applicant; Bombay High Court Criminal Appellate Jurisdiction; Interim Application No. 635 of 2026; Gauri Godse, J.
What did the court decide?
The Interim Application is allowed; the time granted by order dated 12th November 2025 to file the appeal before the Sessions Court is extended by four weeks from the date of the order, as a last chance. ¶23