Gvpr Engineers Limited v. The Maharashtra State Electricity Distribution Co. Ltd.
Case brief
What is this about?
Bombay High Court; Arif S. Doctor, J.; GVPR Engineers Limited; Maharashtra State Electricity Distribution Co Ltd (MSEDCL); Commercial Arbitration Application No. 528 of 2019; Interim Application No. 247 of 2025; Section 11; condonation of delay; delay of 1678 days; restoration of arbitration application; rejection order dated 20/02/2020; dismissed for want of removal of office objections; 7th October 2021 dismissal; relocation of matter to Pune; office objections; substantive interest of justice; heard on merits; decided 30th March 2026; Rajni Divkar; Pratik Divkar; Anuj Jaiswal; Little & Co.
What did the court decide?
Condonation of the delay of 1678 days in filing the Interim Application, setting aside of the rejection order dated 20/02/2020, and restoration of Commercial Arbitration Application (L) No. 528 of 2019 to the file of this Court.