Ansari Mohammed Abubakar v. Union of India through General Manager, Mumbai
Case brief
What is this about?
FA(ST) 23560/2022; IA No. 1965/2024; condonation of delay of ten days; Original Claimant Ansari Mohammed Abubakar; Railway Claims Tribunal Mumbai; Application No. OA(IIu)/MCC/0877/2014; Judgment and Order dated 18.05.2022 challenged; appeal admitted; R & P called for; final hearing 07.05.2026; compilation due 30.04.2026; Union of India through General Manager Central Railway Mumbai (unrepresented); Justice Rajesh S. Patil; High Court of Judicature at Bombay, Civil Appellate Jurisdiction.
What did the court decide?
Interim Application No. 1965 of 2024 allowed in terms of prayer clause (7), condoning the ten-day delay in filing the First Appeal; First Appeal (ST) No. 23560 of 2022 admitted; R & P called for; matter listed for Final Hearing on 07.05.2026; Appellant directed to file compilation of documents by 30.04.2026. ¶23