The New India Assurance Co. Ltd. v. Drupadabai Ladba Jondhale Since Deceased Thr. Lrs. Valmik Ladba Jondhale and Ors.
Case brief
What is this about?
Bombay High Court interlocutory order (Jitendra Jain, J., 07 April 2026) in IA No. 1743 of 2025 in First Appeal (ST.) No. 18290 of 2011 (The New India Assurance Co. Ltd. v. Drupadabai Ladba Jondhale & Ors.): condonation of delay in moving the application; permission to implead legal heirs of original respondent no.1; amendments within four weeks; application disposed of. No statute or precedent discussed.
What did the court decide?
Delay in taking out the Interim Application condoned; legal heirs of original respondent no.1 permitted to be brought on record; necessary amendments to be carried out within four weeks; Interim Application disposed of. ¶¶14