Isak Maknojia v MCGM; Bombay High Court; Farhan P. Dubash; Interim Application 1244 of 2026; Appeal from Order 18 of 2022; regularization application online portal; EOBD; DCPR 2034; letter dated 23 July 2025 delivery not proven; rejection letter 28 January 2026; removal within ten days; demolition threatened; six weeks protection; order dated 25 March 2025; offending structure; B Ward MANDI; File No. P–29583/2026/(1/1921)/B-Ward/MANDI; decide within 12 weeks; on or before 8 May 2026; no coercive action; impugned notice; no further construction; no third party rights; undertaking to remove; disposed; no costs; 13 February 2026.
What did the court decide?
Interim Application disposed of in terms of the Court's order, with no order as to costs: (i) MCGM to decide the online Regularization Application (File No. P–29583/2026/(1/1921)/B-Ward/MANDI, dated 10 February 2026) in accordance with law within 12 weeks, on or before 8 May 2026; (ii) no coercive action against the offending structure pursuant to the impugned notice until that decision; (iii) if adverse, the earlier protection continues for a further six weeks from communication of the adverse decision; (iv) Applicant free to adopt appropriate legal proceedings against an adverse decision; (v) no further construction, no third-party rights, no parting with possession; (vi) subject to the challenge and its result, removal of the structure per the undertaking recorded in the order dated 25 March 2025.