Executive Engineer, Nimna Painganga Project, Yavatmal Division, Yavatmal v. Prashant Krushnarao Nimje and 2 Others
Case brief
What is this about?
Withdrawal of compensation amount deposited in High Court; CAF No. 2010/2021 in First Appeal No. 534/2021; 50% of deposit released to Respondent No.1 Prashant Krushnarao Nimje on usual undertaking; balance directed to Fixed Deposit with nationalized bank; no objection by appellant Executive Engineer, Nimn Painganga Project (VIDC); advocates A.M.Kukday, A.B.Nakshane, T.Khan (AGP); Bombay High Court, Nagpur Bench; decided 13/10/2021.
What did the court decide?
Civil Application No. 2010/2021 partly allowed: 50% of the compensation amount deposited in Court to be released to Respondent No.1 on furnishing the usual undertaking; balance to be kept in Fixed Deposit with any nationalized bank. The order does not dispose of the main appeal. ¶14